New renewable and firming capacity

The increase in FY24 was due to the commencement of construction of the 500 MW Liddell Battery.

FY20

FY21

FY22

FY23

FY24

New renewable and firming capacity (MW)

NR

NR

NR

478

978

Notes

Comprises Liddell Battery (500 MW) (under construction during the period), Broken Hill Battery (50 MW) (under commissioning during the period), Torrens Island Battery (250 MW) and Rye Park Wind Farm PPA (178 MW). Does not include the 14 MW upgrade currently underway at Clover Power Station (hydro).

Measured as new firming and renewable capacity in construction, delivery or contracted from 1 July 2022 onwards. Excludes projects that were already operational during FY23.

NR: Not reported